There is a significant amount of disruption coming from various level crossing closures on the railway line through the parish. Below is the relevant text of the email from network rail. They have set up a dedicated webpage at https://www.networkrail.co.uk/NorthDownsLine which will be regularly updated as the work progresses.


Dear Stakeholder, 

Upcoming engineering work between Guildford and Reigate, Saturday 1 to Sunday 16 February 2025

I am writing to remind you that between Saturday 1 and Sunday 16 February, Network Rail engineers will be carrying out a large programme of works on the North Downs line, between Guildford and Reigate.

These works include renewing the tracks over a bridge on the River Wey in Shalford, stabilising an embankment in Gomshall and renewing the signalling and level crossings along the line.

Level crossing works

At times we will need to close the level crossing we are upgrading to carry out the work, and signed diversions will be in place. During full road closures, pedestrians won’t have access to the crossings, but minibuses will be arranged to help any pedestrians around the closure. Half road closures close the crossings to single lane access with temporary traffic lights, and pedestrians can use the crossing.

Please find the list of road closures below:

Tangley Level Crossing, A248, Chilworth, Guildford GU4 8NE

00:35 to 05:20 Monday 3 FebruaryFull Closure
00:35 to 05:20 Tuesday 4 FebruaryFull Closure

Chilworth Level Crossing, Sampleoak Lane, Chilworth, Guildford GU4 8QN

00:15 Saturday 1 January to 06:00 Sunday 2 FebruaryFull Closure – pedestrians can cross with marshall
Sunday 2 to Friday 7 February (Overnight Closures 23:00 – 06:00)Half Closure with Temporary Obstruction Boards
Friday 7 to Saturday 8 February (Overnight Closures 23:00 – 11:00)Full Closure – pedestrians can cross with marshall
Saturday 8 to Thursday 13 February (Overnight Closures 23:00 – 05:00)Full Closure – pedestrians can cross with marshall
Thursday 13 February (Daytime Closure 07:00 – 17:00)Full Closure – pedestrians can cross with marshall
Thursday 13 to Sunday 16 February (Overnight Closures 23:00 – 05:00)Full Closure – pedestrians can cross with marshall
Sunday 16 to Monday 17 February(Overnight Closures 21:00 – 05:00)Full Closure – pedestrians can cross with marshall

Brook Level Crossing, New Road, Albury, Guildford GU5 9DJ

23:00 Friday 31 January to 06:00 Monday 17 February Full Closure

Burrows Lane Level Crossing, Queen St, Gomshall, Guildford GU5 9LR

23:00 Friday 31 January to 06:00 Monday 17 FebruaryFull Closure

Additional works

At the River Wey Railway Bridge, we are carrying out track renewals, while on the remainder of the line, we are continuing with our re-signalling works which includes laying new cable, substantial heavy foundation works at Burrow and Brook Level Crossings as well as cutting stabilisation.